Theia

Article

Auvere Power Plant Restarts Operations Ahead of Schedule Amid High Electricity Prices

POWER GRIDS & TRANSMISSION

Enefit Power completed repairs at the Auvere Power Plant ahead of schedule on February 4, synchronizing it with the grid. The plant, now operational, is expected to operate alongside the Eesti Power Plant’s sixth unit, under repair until February 12.

Despite the restart, it is uncertain how much this will affect high electricity prices in Estonia, where demand currently exceeds 5,000 megawatts. January's average electricity price reached €154.44 per megawatt-hour, the highest since 2024.

Auvere Power Plant Restarts Operations Ahead of Schedule Amid High Electricity Prices
Feb 7, 2026, 9:49 AM

No comments yet. Be the first to share your thoughts!