Theia

Article

Grant PUD to Expand Mountain View Substation in Quincy for Transmission Capacity Increase

POWER GRIDS & TRANSMISSION

Grant County Public Utility District plans a major expansion of its Mountain View Substation in Quincy to enhance transmission capacity and reliability. The project has received a Determination of Non-Significance under the State Environmental Policy Act.

Construction is set to begin on May 20, 2026, and finish by November 24, 2027. The expansion will enable the substation to serve up to 650 megawatts of load.

Grant PUD to Expand Mountain View Substation in Quincy for Transmission Capacity Increase
Feb 12, 2026, 6:00 AM

No comments yet. Be the first to share your thoughts!