Jemena and AER Dispute $260 Million Over Power Grid Upgrades Amid Melbourne's Data Centre Growth
POWER GRIDS & TRANSMISSION
Jemena is in a $260 million dispute with the Australian Energy Regulator (AER) regarding funding for power grid upgrades needed for expected data centre demand in Melbourne's north-west. Jemena seeks $2 billion in revenue to support a doubling of demand by 2031, while the AER suggests only $1.7 billion is necessary, citing overestimated growth predictions. The outcome may impact customer bills and energy supply reliability as the government supports scrutiny of Jemena's plans.

Feb 28, 2026, 3:51 PM