NHE Housing Project in Katima Mulilo Progresses with 546 Houses Planned
FLOW CONTROL
The NHE's housing project at Chotto Extension 55-56 in Katima Mulilo is 50% land serviced and valued at N$60 million, expected to complete by July 2026. The Katima Mulilo Town Council provided land for 546 houses at no cost.
NHE invested N$55.4 million, creating over 70 local jobs. The project includes four pump stations for sewer reticulation. Additionally, NHE has launched a National Informal Settlement Upgrading Programme aiming for 10,000 houses annually.

Feb 23, 2026, 11:37 AM