AIC Mines Intersects Mineralisation at Jericho Copper Project in Queensland

STRATEGIC MINERALS

AIC Mines has intersected mineralisation at its Jericho copper project in Queensland through an access drive from the Eloise mine. The Jericho access drive has reached the J1 lens, providing direct access to the deposit.

The project hosts a resource of 19.2 million tonnes at 2.0% copper and 0.4 g/t gold. Development began in May 2024 and has advanced 2.35 km underground. AIC plans to expand the Eloise processing facility to 1.1 million tonnes per annum by December 2026.

AIC Mines Intersects Mineralisation at Jericho Copper Project in Queensland
Feb 9, 2026, 1:46 PM