El-Mor Advances Two Battery Energy Storage Projects in Romania for Rapid Delivery
ENERGY STORAGEPOWER GRIDS & TRANSMISSION
El-Mor Electric Installations & Services is progressing with two stand-alone Battery Energy Storage System (BESS) projects in Romania: BRADU BESS in Argeș and BRAZI BESS in Prahova. Each project targets 203 MW and up to 800 MWh capacity, with RTB planned for Q1 2026 and commissioning in H1 2027. Both projects already have ATR approvals and aim to connect to Transelectrica's substations.

Feb 12, 2026, 6:10 AM