NEC Modifies Strategy for Chaira Pumped Storage Plant Hydro Unit Replacement

HYDRO POWERFLOW CONTROL

The National Electric Company (NEC) will shift to three smaller contracts for replacing hydroelectric units at the Chaira Pumped Storage Power Plant. This decision follows unsuccessful attempts to secure a contractor for a large combined contract. The third unit is expected to resume operation in April, while work on a temporary repair for the first unit is ongoing, with a full replacement planned for the future.

NEC Modifies Strategy for Chaira Pumped Storage Plant Hydro Unit Replacement
Feb 22, 2026, 1:05 PM