Texmaco Completes Commissioning of Hydro-Mechanical Systems for 2,000 MW Subansiri Lower Project
HYDRO POWER
Texmaco Rail & Engineering has successfully completed the commissioning of hydro-mechanical systems for the 2,000 MW Subansiri Lower Hydroelectric Project on the Arunachal Pradesh-Assam border. As the sole contractor, Texmaco oversaw the design and implementation of essential systems for the project's eight generating units, each with a capacity of 250 MW. The commissioning process began in late 2025, with the first unit starting wet commissioning on October 24, 2025, and subsequent units scheduled for phased commissioning through FY27.

Jan 9, 2026, 6:07 AM